“Developing a Festival” Appendix “S” – Critical Path Chart Sample

 

Task Name        Duration  Start             Finish

 

Fixing Date of Festival              4d   Mon 2/26/07        Thu 3/1/22               

Estimate number of attendees 4d    Mon 2/26/07        Thu 3/1/22               

Find and book location             8d   Mon 2/26/07        Wed 3/7/22             

Determine admission prices   10d   Mon 2/26/07        Fri 3/9/22               

Determine festival duration    10d    Mon 2/26/07        Fri 3/9/22               

Determine festival theme        10d   Mon 2/26/07        Fri 3/9/22               

Determine festival program    14d   Mon 2/26/07        Thu 3/15/22           

Book vendors                         14d   Mon 2/26/07        Thu 3/15/22           

Create advert/promo plan       21d   Mon 2/26/07        Mon 3/26/22   

Register website                     21d   Mon 2/26/07        Mon 3/26/22           

Develop website                     30d   Mon 2/26/07        Fri 4/6/22               

Sponsorship plan                   45d    Mon 2/26/07        Fri 4/27/22               

Benefactor program               60d    Mon 2/26/07        Fri 5/18/22               

Special considerations          60d    Mon 2/26/07        Fri 5/18/22               

Hold event                             61d    Mon 2/26/07        Mon 5/21/22